Date / Time (UTC)Task / MilestoneDescription / NotesStatus
July 9, 2025πŸ“£ User Notification SentEmail alert sent to all users regarding planned downtime on July 5.

DONEΒ 

July 12, 2025πŸ“¦ Final Backup & Pre-checksFull site backup, plugin compatibility validation, dry-run tested.

DONE

July 12, 2025πŸ›  Final Plugin BuildsRebuilt plugins for Gerrit 3.11.2 compatibility.

DONE

July 12, 2025 15:00🚧 Start Maintenance WindowSite taken offline, migration started.

DONE

July 12, 2025 15:10πŸ”„ Migration Begins (2.16 β†’ 3.11.2)Incremental upgrades performed through required intermediate steps.

DONE

July 12, 2025 ~21:00πŸ” Index Rebuild & Configuration UpdatesReindexing data, updating config for 3.x, plugin re-deployment.

DONE

July 12, 2025 ~22:00βœ… Migration CompleteAll services validated, site brought back online.

DONE

July 12, 2025 ~23:00πŸ“¬ Post-Maintenance NotificationEmail sent confirming successful upgrade and any key changes.

DONE

July 13-19, 2025πŸ§ͺ Post-upgrade Monitoring & Support

Monitor logs, performance, address issues raised by users.


IN PROGRESS